April 27, 2026 – Vancouver, British Columbia – Graphite One Inc. (TSX-V: GPH; OTCQX: GPHOF) (“Graphite One” or the “Company”), a developer of a complete U.S.-based advanced graphite supply chain, today provided an update on the permitting progress of its flagship Graphite Creek Project under the FAST-41 federal permitting program.
The Graphite Creek Project — planned as an open-pit graphite mine and associated mineral processing plant located approximately 60 km (37 miles) north of Nome, Alaska — was accepted as a FAST-41 “covered project” on June 2, 2025, becoming the first Alaska mining project to be listed on the FAST-41 Federal Permitting Dashboard. Following the 60-day Coordinated Project Plan (“CPP”) process, the detailed permitting timetable was publicly posted on August 5, 2025. The CPP established a clear 13.5-month schedule for the required federal environmental reviews and authorizations, with a projected completion date of September 29, 2026.